**VENEZUELAN PORT BOTTLENECKS IMPOSE DE FACTO CAP ON CRUDE EXPORTS**
Aging infrastructure, frequent power outages, and quality control issues at Venezuela’s dilapidated marine terminals are severely restricting the nation’s resurgent crude production. According to shipping data, industry documents, and sources, tankers are now facing wait times of up to 30 days to load cargoes.
These chronic delays are disrupting a U.S.-backed plan to rapidly scale up Venezuelan oil exports following a major agreement with global trading houses. The scramble for terminal space is expected to intensify as partners of state-run energy firm PDVSA prepare to market their shares of production independently under newly revised contract terms.
The current shipping backlog is the worst since late last year, when a U.S. naval blockade—part of a strategy that led to the January 3 capture of former President Nicolas Maduro—severely disrupted maritime traffic. Since then, interim leader Delcy Rodriguez has aligned with Washington’s efforts to revive the nation’s oil sector.
However, vessel monitoring data reveals that despite rising crude output, high global demand, and the drawdown of inventories, PDVSA and its partners have been unable to push exports past 1.25 million barrels per day (bpd). This stands in stark contrast to two decades ago, when Venezuela produced over 3 million bpd and its terminals efficiently exported more than 2.5 million bpd, with turnaround times of less than a week.
The persistent loading delays are triggering disputes over demurrage fees, crude quality, and vessel contamination.
“The transfer of crude from storage tanks to vessels is incredibly slow, forcing tankers to remain at the docks far past their scheduled loading windows,” a PDVSA source noted. “Furthermore, if a ship arrives to discharge imports, the process is delayed even longer due to a lack of fuel storage capacity.”
Neither PDVSA nor Venezuela’s oil ministry responded to requests for comment.
**Congestion at Jose Terminal**
The maritime traffic jam is highly visible at the country’s anchorages, particularly near the Jose terminal on the northeastern coast, which handles roughly 70% of Venezuela’s total exports. Internal shipping reports show frequent operational halts this year due to equipment failures, power outages, and product quality issues during loading operations.
Even long-term partners with historically privileged access to infrastructure, such as U.S. major Chevron, are seeking workarounds. Sources indicate the company has requested access to alternative ports previously reserved for domestic shipping to bypass the bottlenecks. Chevron did not comment on the matter.
While the eased U.S. sanctions have allowed major trading houses like Vitol and Trafigura to export over 140 million barrels of crude and fuel this year to markets in the U.S., Europe, and India, the underlying infrastructure remains a critical weak point. Washington’s $100 billion energy reconstruction plan focuses primarily on boosting crude extraction, leaving midstream and downstream projects—such as refinery and terminal repairs—largely unprioritized.
At recent energy conferences in Houston, U.S. and Venezuelan officials acknowledged these infrastructure hurdles but expressed optimism that fresh investments could resolve them.
“We are currently in a recovery phase, and the physical infrastructure is there,” said PDVSA Vice President Jovanny Martinez. “However, there are deficiencies, and operational reliability must be improved.”
**Rust, Leaks, and Logistical Hurdles**
The congestion at the Jose and Pozuelos anchorages is compounded by legacy issues. The docks remain cluttered with abandoned vessels from the sanctions era, including blacklisted tankers that cannot leave.
One such vessel, flying a false Guyanese flag and formerly known as the *Syrma* (now renamed the *Consul*), has been docked at PDVSA’s Guaraguao port for two years to avoid U.S. seizures. It occupies valuable berth space at a time when foreign companies are desperate for capacity. According to a terminal worker, only two of Guaraguao’s seven docks were operational in mid-August.
The shortage of functional berths has forced some buyers to use alternative terminals or ship-to-ship transfer zones prone to oil leaks. These leaks frequently stain vessel hulls, leading to further cleaning delays and added costs.
Additionally, PDVSA is facing mounting demurrage charges for delayed vessels, which the state company has agreed to settle only using crude oil. At the same time, PDVSA is requiring new buyers to pay for cargoes upfront without credit, complicating the invoicing process when customers demand discounts for quality issues or delays.
The transition of dozens of oil contracts to new terms under a sweeping energy reform that took effect in late July is expected to further strain the country’s port infrastructure. Despite the pressure, sources indicate that PDVSA intends to maintain strict control over its terminals and cargo scheduling for the foreseeable future.